Glaziers Professional Corp

Accounting Dec 01, 2020

Glaziers Professional Corp. manufactures customized frames for pictures and certificates. Sales for August are expected to be 10,000 units of various sizes. The average frame requires:

Wood: 4 metres

Glass: One square metre

Backing: Two square metres

Beginning inventory includes 1,500 metres of framing, 500 square metres of glass, and 500 square metres of backing. Current prices are $0.30 per metre for framing, $6.00 per square metre for glass, and $2.25 per square metre of backing. Ending inventory should be 150% of beginning inventory. Purchases are paid for in the same month acquired.

Required:

a) Determine the quantity of framing, glass, and backing required to be purchased in August.

b) Determine the total costs of direct materials for August purchases.

Expert Solution

a) Purchase quantity = Materials requirements for 10,000 units + Ending inventory - Beginning inventory

1. Calculation of materials requirement for 10,000 units:

  For an average frame For 10,000 units
wood(framing) 4 metres 4*10,000 = 40,000 metres
Glass 1 square metre 1*10,000 = 10,000 square metres
Backing 2 square metres 2*10,000 = 20,000 square metres

2. Calculation of ending inventory (150% of beginning inventory):

  Beginning inventory Ending inventory needed:
Framing 1,500 metres 1,500*150% = 2,250 metres
Glass 500 Square metres 500*150% = 750 square metres
Backing 500 Square metres 500*150% = 750 square metres

3. Calculation of purchase quantity for august = materials required for 10,000 units + Ending inventory - Beginning inventory

Framing = 40,000 + 2,250 - 1,500 = 40,750 metres

Glass = 10,000 + 750 - 500 = 10,250 square metres

Backing = 20,000 + 750 - 500 = 20,250 square metres

b) Total costs of direct materials purchased in August:

Direct materials Purchase quantity Rate per unit of material Total cost
Framing 40,750 metres $0.30 per metre $0.30 * 40,750 = $12,225
Glass 10,250 square metres $6.00 per square metre $6.00 * 10,250 = $61,500
Backing 20,250 square metres $2.25 per square metre $2.25 * 20,250 = $45,562.5
Total costs of direct materials purchased in august (Framing + Glass + Backing) $119,287.5
Archived Solution
Unlocked Solution

You have full access to this solution. To save a copy with all formatting and attachments, use the button below.

Already a member? Sign In
Important Note: This solution is from our archive and has been purchased by others. Submitting it as-is may trigger plagiarism detection. Use it for reference only.

For ready-to-submit work, please order a fresh solution below.

Or get 100% fresh solution
Get Custom Quote
Secure Payment