Fill This Form To Receive Instant Help

Help in Homework
trustpilot ratings
google ratings


Homework answers / question archive /  A manufacturer is designing a product layout for a new product production

 A manufacturer is designing a product layout for a new product production

Economics

 A manufacturer is designing a product layout for a new product production. It plans to use a production line for 8 hours per day in order to meet forecasted demand of 100 units per day. The product requires 7 tasks in total. These tasks are namely, A, B, C, D, E, F, and G respectively. Task A does not have any predecessor to start. To start Task B, it requires Task A to be completed. Starting tasks needs, the task B to be completed. Also, starting task D needed task B to be completed. Task E can only start upan completion of Task C. Whereas starting task F needs the completion of both the tasks D and E. Finally, starting task G needed, task F to be completed. The processing times for tasks, A, B, C, D, E, F, and G are 28, 2.1,0.9, 1.0, 1.2, 1.8, are 4.7 minutes respectively. How many minimum numbers of workstations are needed? Select one a. 4 b. None is the correct answer 08 d. 6 e. 2 A manufacturer is designing a product layout for a new product production. It plans to use a production line for 8 hours per day in order to meet forecasted demand of 100 units per day. The product requires 7 tasks in total. These tasks are namely, A, B, C, D, E, F and G respectively. Task A does not have any predecessor to start. To start Task B, it requires Task A to be completed. Starting tasks needs, the task B to be completed. Also, starting task D needed task B to be completed. Task E can only start upon completion of Task C. Whereas starting task F needs the completion of both the tasks D and E. Finally, starting task G needed, task F to be completed. The processing times for tasks, A, B, C, D, E, F, and G are 2.8, 2.1,0.9, 1.0, 1.2, 1.8, are 4.7 minutes respectively. Applying the most following tasks rule for balancing the assembly line, with ties broken according to longest task time first, the tasks that will be assigned to the FIRST workstation are Select one: a. A, B, and C b. None is the correct answer C. A only d. A,B 

Option 1

Low Cost Option
Download this past answer in few clicks

2.89 USD

PURCHASE SOLUTION

Already member?


Option 2

Custom new solution created by our subject matter experts

GET A QUOTE