Fill This Form To Receive Instant Help

Help in Homework
trustpilot ratings
google ratings


Homework answers / question archive / Brian worked 48 hours during the week

Brian worked 48 hours during the week

Finance

Brian worked 48 hours during the week. His normal working week consists of 40 hours, of which 34 hours were spent on production while the remaining 6 hours were idle time. Overtime is paid at time and a half. However, it is the policy of the company to pay staff 200% of the normal wage rate after the first three hours of overtime on any working day. Brian worked 5 hours of overtime on a job for which the customer required the work to be completed on the same day. Brian’s normal wage rate is $13 per hour. The rest of the week Brian did not work more than three hours of overtime on any one day.

(Enter amount only, do not use dollar signs or commas)

1) What is Brian's gross pay for the week? (1 mark) Answer

2) How much of Brian's gross pay would be charged as direct labour? (1 mark) Answer

3) What is the cost of idle time? (1 mark) Answer

4) What is the amount of the overtime premium paid? (1 mark) Answer

5) How much of Brian's gross pay is charged as a manufacturing overhead cost? (1 mark) Answer

pur-new-sol

Purchase A New Answer

Custom new solution created by our subject matter experts

GET A QUOTE

Answer Preview

Type of Work No of Hours Wage rate per Hr Total Wage Cost Category
Production Hours                            34.00 $                   13.00 $                     442.00 Direct Labor
Idle Hours                              6.00 $                   13.00 $                       78.00 Manufacturing Overhead
First Three Hrs of 5 Hr Overtime paid @150%                              3.00 $                   19.50 $                       58.50 Manufacturing Overhead
Remaining 2 Hrs of 5 Hrs Overtime @200%                              2.00 $                   26.00 $                       52.00 Manufacturing Overhead
Remaining 3 hrs Overtime on other days @150%                              3.00 $                   19.50 $                       58.50 Manufacturing Overhead
Total Work in the Week                            48.00   $                     689.00  
ans 1 Gross Pay of Brian during the week=                               689
ans 2 Total Gross pay chargable as Direct Labor =                               442
Ans 3 Cost of Idle time =                                  78
Asn 4 Over tine premium:  
  Total Overtime hours done                                    8
  Normal wage @$13/hr for the overtinme hrs=                               104
  Actual Overtime payment =                               169
  Overtime premium =                                  65
     
Ans 5 Amount of Gross pay charges as Manufacturing                               247
  overhead =