Homework answers / question archive / Prepare additional EV curves starting with the work package example presented from Chapter 8, Figure 8
Prepare additional EV curves starting with the work package example presented from Chapter 8, Figure 8.3. Status the work package at day 12. Draw an EV curve where the foreman is over budget and behind schedule and another where the team is on budget and ahead of schedule. Prepare a narrative explaining why these situations might be occurring.