MRP Class Assignment #6
Product A is made of Four units of B and two units of C
Math
Share With
MRP Class Assignment #6
Product A is made of Four units of B and two units of C. B is made of three units of D and two E. C is made of three units of F and one unit of E. Lead times for purchase of each unit are: A takes one week, B takes two weeks, C takes one week. D and E take 2 weeks and F takes 3 weeks. Assume that there is a demand for 150 units of A in week 8. There is on-hand inventory of 100 units of B, and 20 units of C. There is a scheduled receipt of E for 500 units in week three. Assume all items are purchased L4L except for item D which is ordered in multiples of 50, F which is ordered in multiples of 100 and E which is 500
Show the bill of materials (product structure tree)
Develop an MRP planning schedule showing gross and net requirements and order release and order receipt dates.
Product A is an end item and is made from three units of B, three units of C and two units of D. B is made of three units of E and two of F. C is made of two units of F and one of D. A and B have a lead time of one week. C and D have lead times of two weeks, and E and F have lead times of three weeks. Lot sizes for A, B and D are L4L. Item C has a lot size of 60. E and F have a lot size of 100. There is 50 units of item B on hand, and 30 units of item A. There is a scheduled receipt for 50 units of item F in week three.
Show the bill of materials (product structure tree)
If 125 units of A are required in Week 8, develop the MRP planning schedule, specifying when items are to be ordered and received.