It's the end of month 4 of your 6 month project and your performance cost reports have arrived
It's the end of month 4 of your 6 month project and your performance cost reports have arrived.
So far, your plan is to have $500,000 worth of work to be completed.
Your project team actually accomplished $600,000 worth of work.
Total expenditures for the completed work is $650,000.
What is the earned value, actual cost, and planned value?