University of California, Los Angeles RQMCMB 2 Quiz 2 1)A method used for establishing a logical framework for identifying the required activities for the project is called: 2
University of California, Los Angeles
RQMCMB 2
Quiz 2
1)A method used for establishing a logical framework for identifying the required activities for the project is called:
2. = 27; activity times are a = 4, b = 6, c = 8.
- A nonlinear cost related to order size is the cost of:
- A pchart would be used to monitor .
- A PERT/CPM activity has an optimistic time estimate of three days, a most likely time estimate of eight days, and a pessimistic time estimate of 10 days. The expected time (in days) of this activity is:
- A point which is outside of the lower control limit on an Rchart: C. should be investigated because an assignable cause of variation might be present
- more complex projects, is the:
- A process results in a few defects occurring in each unit of output. Longrun, these defects should be monitored with .
- A recent effort to expand the scope of production resource planning by involving other functional areas in the planning process has been:
- A risk avoider would want safety stock.
- A sequence of activities that leads from the starting node to the finishing node is called a
- A shift in the process mean for a measured characteristic would most likely be detected by a:
- A timeordered plot of sample statistics is called a(n) chart.
- A visual depiction of the subassemblies and components that are needed to produce and/or assemble a product is called a(n):
- Accommodating peak demands and effectively using labor resources during periods of low demand would be the goal of aggregate planners in
- Activity 45 in a network diagram has an optimistic time estimate of five days, a most likely time estimate of seven days, and a pessimistic time estimate of 10 days. Its expected time is approximately:
- Activity 78 is directly preceded by two activities—activity 57 and activity 67. Activity 57 has an expected time of five and an ES time of six. Activity 67 has an expected time of seven and an ES time of seven. Activity 78 has an expected time of 10. The ES for activity 78 is:
- Activity C has an early start time of 8, an early finish time of 12, a latest start time of 13, and a latest finish time of 17. Its slack is:
- Activity J has a duration of 7 and an earliest finish time of 21. If J's latest start time is 16, this must mean that J's slack is .
- Aggregate planners attempt to balance:
- Aggregate planning is capacity planning for:
Expert Solution
PFA
Archived Solution
Unlocked Solution
You have full access to this solution. To save a copy with all formatting and attachments, use the button below.
Already a member? Sign In
Important Note:
This solution is from our archive and has been purchased by others. Submitting it as-is may trigger plagiarism detection. Use it for reference only.
For ready-to-submit work, please order a fresh solution below.
For ready-to-submit work, please order a fresh solution below.
Or get 100% fresh solution
Get Custom Quote