Fill This Form To Receive Instant Help

Help in Homework
trustpilot ratings
google ratings


Homework answers / question archive / Last month, 75,000 kilograms of direct materials were purchased, and 71,000 kilograms were used

Last month, 75,000 kilograms of direct materials were purchased, and 71,000 kilograms were used

Accounting

Last month, 75,000 kilograms of direct materials were purchased, and 71,000 kilograms were used. If the actual purchase price per kilogram was $0 50 more than the standard purchase price per kilogram, what was the materials price variance? 
A. $2,000 favourable. B. $35,500 unfavourable. C. $37,500 favourable. D. $37,500 unfavourable. 

pur-new-sol

Purchase A New Answer

Custom new solution created by our subject matter experts

GET A QUOTE

Answer Preview

Answer

B .

Explanation

Computation of Material Price Variance:

Material Price Variance = Actual Quantity*(Actual Price - Standard Price)

Here,

Actual Quantity (AQ) = 71,000 Kilograms

Standard Price = x

Actual Price = 0.5+x

 

Material Price Variance = 71,000(($0.5+ $x - $x) 

= 71,000($0.5) 

Material Price Variance $35,500 Unfavorable

 