Homework answers / question archive / The bottom-up approach for estimating times and costs that uses costs from past projects that were similar to the current project is known as     Detailed WBS work package estimates

The bottom-up approach for estimating times and costs that uses costs from past projects that were similar to the current project is known as     Detailed WBS work package estimates

Business

The bottom-up approach for estimating times and costs that uses costs from past projects that were similar to the current project is known as

   

Detailed WBS work package estimates.

   

Template method.

   

Time-phased cost estimates.

   

Function point method.

   

Phase estimating.