Homework answers / question archive / Emily has recently learned that she needs to reduce the duration of her project to meet an imposed deadline

Emily has recently learned that she needs to reduce the duration of her project to meet an imposed deadline

Business

Emily has recently learned that she needs to reduce the duration of her project to meet an imposed deadline. She has calculated the crash cost per unit and knows the maximum units each activity can be reduced. What is the next step?

   

Find the activity with the highest crash cost

   

Calculate the crash point

   

Calculate the optimum cost-time point

   

Find the activity with the lowest crash cost

   

Identify the critical path