Homework answers / question archive / Trico Company set the following standard unit costs for its single product

Trico Company set the following standard unit costs for its single product

Accounting

Trico Company set the following standard unit costs for its single product.

   Direct materials (30 Ibs. @ $4.80 per Ib.)$144.00Direct labor (6 hrs. @ $14 per hr.) 84.00Factory overhead—variable (6 hrs. @ $7 per hr.) 42.00Factory overhead—fixed (6 hrs. @ $9 per hr.) 54.00Total standard cost$324.00

The predetermined overhead rate is based on a planned operating volume of 80% of the productive capacity of 57,000 units per quarter. The following flexible budget information is available.

 Operating Levels  70% 80% 90%Production in units 39,900 45,600 51,300Standard direct labor hours 239,400 273,600 307,800Budgeted overhead      Fixed factory overhead$2,462,400$2,462,400$2,462,400Variable factory overhead$1,675,800$1,915,200$2,154,600

During the current quarter, the company operated at 90% of capacity and produced 51,300 units of product; actual direct labor totaled 304,800 hours. Units produced were assigned the following standard costs.

   Direct materials (1,539,000 Ibs. @ $4.80 per Ib.)$7,387,200Direct labor (307,800 hrs. @ $14 per hr.) 4,309,200Factory overhead (307,800 hrs. @ $16 per hr.) 4,924,800Total standard cost$16,621,200

Actual costs incurred during the current quarter follow.

   Direct materials (1,519,000 Ibs. @ $7.30 per lb.)$11,088,700Direct labor (304,800 hrs. @ $13.00 per hr.) 3,962,400Fixed factory overhead costs 2,337,000Variable factory overhead costs 2,187,800Total actual costs$19,575,900(a) Compute the variable overhead spending and efficiency variances. (Round "cost per unit" and "rate per hour" answers to 2 decimal places.)

AH = Actual Hours

SH = Standard Hours

AVR = Actual Variable Rate

SVR = Standard Variable Rate

(b) Compute the fixed overhead spending and volume variances. (Round "cost per unit" and "rate per hour" answers to 2 decimal places.)

AH = Actual Hours

SH = Standard Hours

AFR = Actual Fixed Rate

SFR = Standard Fixed Rate

(c) Compute the total overhead controllable variance.