Homework answers / question archive / If the food has to be delivered by 12:00 noon at the farthest school from the Vasanthapura kitchen (which takes 4 hours to reach), what are the lower and upper specification limits for completion of the first batch of Sambar? If the cooking starts at 5:00am, calculate the corresponding Sigma score (assume that the standard deviation for Sambar cooking is 10 minutes
If the food has to be delivered by 12:00 noon at the farthest school from the Vasanthapura kitchen (which takes 4 hours to reach), what are the lower and upper specification limits for completion of the first batch of Sambar? If the cooking starts at 5:00am, calculate the corresponding Sigma score (assume that the standard deviation for Sambar cooking is 10 minutes