Homework answers / question archive / Question 1) Which of the following does  NOT help describe a project network?                 Question 2         The amount of delay within a task that will not delay the overall project is known as a               Question 3         The backward pass in project network calculations determines all of the following EXCEPT               Question 4         The forward pass in project network calculations determines all of the following EXCEPT               Question 5         A ________ activity is one that has more than one activity taking place at the same time

Question 1) Which of the following does  NOT help describe a project network?                 Question 2         The amount of delay within a task that will not delay the overall project is known as a               Question 3         The backward pass in project network calculations determines all of the following EXCEPT               Question 4         The forward pass in project network calculations determines all of the following EXCEPT               Question 5         A ________ activity is one that has more than one activity taking place at the same time

Computer Science

Question 1)

Which of the following does  NOT help describe a project network?

     

 

 

     
  • Question 2

 

   
 

The amount of delay within a task that will not delay the overall project is known as a

     

 

 

 

 

  • Question 3

 

   
 

The backward pass in project network calculations determines all of the following EXCEPT

     

 

 

 

 

  • Question 4

 

   
 

The forward pass in project network calculations determines all of the following EXCEPT

     

 

 

 

 

  • Question 5

 

   
 

A ________ activity is one that has more than one activity taking place at the same time.

     
       
  • Question 6

 

   
 

System documentation cannot end until three days after testing has started. This is an example of which kind of lag?

     
       
  • Question 7

 

   
 

________ activities must be completed immediately before a particular activity.

     
       
  • Question 8

 

   
 

One piece of information that the arrows within the Activity-on-Node network can convey is

     
       
  • Question 9

 

   
 

A ________ activity is one that has more than one activity immediately preceding it.

     
       
  • Question 10

 

   
 

Which of the following is  NOT one of the basic rules to follow when developing project networks?

     
       
  • Question 11

 

   
 

Arrows on an activity-on-node (AON) project network represent

     
       
  • Question 12

 

   
 

Information to develop a project network is collected from the

     
       
  • Question 13

 

   
 

Which of the following is true about hammock activities?

     
       
  • Question 14

 

   
 

The minimum amount of time a dependent activity must be delayed to begin or end is referred to as

     

 

 

     
  • Question 15

 

   
 

Which of the following correctly calculates the late start for an activity?

     
       
  • Question 16

 

   
 

On a project network, the activity times are derived from the

     

 

 

     
  • Question 17

 

   
 

Concurrent engineering, which has dramatically reduced the development time for new products, relies on what kind of lag?

     
       
  • Question 18

 

   
 

Tom is responsible for ordering hardware for a custom home his company is building. The contractor installing the hardware is scheduled to start in 5 working days, but the hardware is on backorder and will not arrive for another 9 working days. Fortunately, Tom has 10 days of slack; however, he shares this slack with the hardware installer. He will have to let the contractor know that the hardware will be ready 4 days later than expected and that the slack for the installer has been reduced by 4 days. Tom and the installer share 10 days of

     

 

 

     
  • Question 19

 

   
 

Activities which can take place at the same time are termed

     

 

 

 

     
  • Question 20

 

   
 

The likelihood the original critical path(s) will change once the project is initiated is referred to as

     

 

 

     
  • Question 21

 

   
 

Which of the following is provided by both the project network and the work breakdown structure?

     

 

 

     
  • Question 22

 

   
 

A ________ activity is one that has more than one activity immediately following it.

     

 

 

     
  • Question 23

 

   
 

A(n) ________ activity has more than one dependency arrow flowing from it.

     
       
  • Question 24

 

   
 

When translated into a project network, a work package will become

     
       
  • Question 25

 

   
 

Which of the following represents an activity on an activity-on-node (AON) project network?

     

 

 

     
  • Question 26

 

   

________ activities are to be completed immediately following a particular activity.

     

 

 

     
  • Question 27

 

   
 

A sequence of connected, dependent activities is termed a(n)

     

 

 

     
  • Question 28

 

   
 

When completing a backward pass, you carry the LS to the next preceding activity to establish the LF, unless the next preceding activity is a burst activity, in which case you select

     

 

 

     
  • Question 29

 

   
 

A project network provides the basis for ________.

     

 

 

     
  • Question 30

 

   
 

Which of the following correctly calculates the early finish for an activity?

     

 

 

 

 

  • Question 31

 

   
 

When creating a project network, your primary input will be the

     
       
  • Question 32

 

   
 

Which of the following will correctly calculate the total slack in an activity?

     
       
  • Question 33

 

   
 

If, for some reason, the project must be expedited to meet an earlier date, which of the following actions would the project manager take first?

     

 

 

     
  • Question 34

 

   
 

Which of the following can be used without coordinating with managers of succeeding activities?

     

 

 

     
  • Question 35

 

   
 

The assumption that all immediate preceding activities must be 100% complete is too restrictive in some situations. When an activity is broken down into smaller segments in order to start the succeeding activity sooner, this is called

     
  • Question 36

 

   
 

The requirement for a freshly poured foundation to cure before beginning construction is an example of which of the following type of lag?

     

 

 

     
  • Question 37

 

   
 

Bill is building a project network that involves testing a prototype. He must design the prototype (activity 1), build the prototype (activity 2), and test the prototype (activity 3). Activity 1 is the predecessor for activity 2 and activity 2 is the predecessor for activity 3. If the prototype fails testing, Bill must redesign the prototype; therefore, activity 3 is a predecessor for activity 1. This is an example of

     
       
  • Question 38

 

   
 

After the total slack for each activity is identified, the project manager can more easily identify the ________.

     
       

 

Option 1

Low Cost Option
Download this past answer in few clicks

6.87 USD

PURCHASE SOLUTION

Already member?


Option 2

Custom new solution created by our subject matter experts

GET A QUOTE

Related Questions